Yardsticks: Revision of

No.E(MPP)2019/1/12, dated 30.09.2019

Sub: Revision of Yardsticks.             

1. An action plan was formulated by Board for Manpower Management, wherein, it was decided that yardsticks of O&M activities of various departments be revised taking into account technology Upgradation. Outsourcing experience and Benchmarking standards set by different Railways.

2. Accordingly, the yardsticks of certain activities have been revised and enclosed as an Annexure.

3. Henceforth, the requirement of Manpower for the said activities should be calculated based on the revised Yardsticks. The Manpower strength for the existing assets should be reviewed, based on the revised Yardsticks and excess posts be surrendered.

4. All the clarifications/ queries/ references, if any, regarding revised yardsticks are to be made to respective Directorates.

5. This issues with the concurrence of Finance Directorate of the Ministry of Railways.

6. This supersedes all earlier instructions on the Yardsticks of the respective activities, specified in the annexure enclosed.

7. Please acknowledge receipt.

ANNEXURE

1. Yardstick for TRD activity of Electrical Department for Non-Suburban Area is fixed as 0.22/ Track Kilometer, with the following activities to be additionally outsourced.

ActivityRemarks
OHE non-power blockThese activities to be outsourced. Only minimum Supervisory agency and related work to be in house.
OHE other works
PSI MaintenanceAll PSI activities to be outsourced. Only mlnimum supervisory and supporting staff required to monitor.
PSI Operation & Manning
Centralized ActivitiesActivities excluding TPC manning, drawing and technical staff including cledcal staff and Helpers at home.

2. The revised staff Yardsticks for Electric Loco Maintenance (TRS) in loco sheds for different types of locomotives are decided as under; 

Type of LocomotlvesRevised Yardstick
Conventional Loco (freight) with DC drive with Hitachi TM (WAG5) and NAG7.3 staff/ loco
Other conventional locos with DC drive induding coaching locos.3.5 staff/ loco
3-phase locomotive (WAG9, WAP7).2.5 staff/ loco

with activities for outsourcing noted hereunder: 

Already a number of activities are mandatd to be outsourced and are being outsourcecl in various loco sheds. In addition the following activities to be additionally outsourcecl:  

Conventional Locomotives – DC TM overhauling; overhauling of contractors by OEMs; Overhauling of auxiliary motor.

Three Phase Locomotives – Compressor overhauling; TM overhauling; Overhauling of Auxiliary motors.

Further, activities to be outsourced can be identified by respective loco sheds and followed accordingly with the approval of respective PCEE on local need basis and local conditions. 

3. Crew Review – Freight Services:-

After review of various methods followed by different Zonal Railways, it was decided to uniformly adopt on all Zonal Railways, the following method for requirement of freight crew: 

the method of progressive crew hours based on peak six monthly review, i.e. 12 fortnights for the preceding year, should be followed for calculating the bare crew requirement; and

the additional requirement Leave Reserve, Rest Giver etc. shall be governed by extant rules;

4. Coach Maintenance – Electrical: Maintenance & escorting staff for AC coaches as well as maintenance staff for TL coaches.    

Revised yardstick for Coaching stock (Electrical) for maintenance for AC coaches, TL coaches; power cars, escorting staff & train passing staff in the Coaching depot is as under:

 ActivityRevised Yardsticks
(i)TL Coaches 
 (a) Primary maintenance: SG TL/ LHB TL Coaches0.24 staff per coach holding for primary maintenance (ICF).
 (b) Secondary maintenance: SG TL/ LHB TL Coaches0.15 staff per coach handled for primary maintenance (ICF).
 (c) Tain passing for TL/ AC coaches.0.05 per coach holding.
 (d) Sick line attention.0.05 per coach holding.
(ii)AC Coaches: 
 (a) Primary maintenance: 
 ICF & LHB SGAC coach with RMPU.1.10 staff/ coach holding for primary maintenance.
 ICF & LHB EOG AC coach with RMPU.0.8 staff/ coach holding for primary maintenance.
 (b) Secondary maintenance: 
 ICF & LHB SGAC coach with RMPU.0.46 staff/ coach holding for Secondary maintenance.
 ICF & LHB EOG AC coach with RMPU.0.36 staff/ coach holding for Secondary maintenance.
 (c) Sick line attention.0.20 staff per coach.

5. Coach Maintenance – Mechanical

Primary MaintenanceICF/ LHB/ Stock0.85/ Coach (ICF & LHB) with interior amenity attention to be outsourced.
Terminal attention under RPC-4ICF/ LHB/ Stock0.3 Man/ Coach
PF return trains nominated for Rolling in Examination + Clean Train Station etc.ICF/ LHB/ Stock0.2 Man/ Coach
Sick Line 0.12 Man/ Coach
Inspection CarriagePer IC holding1.76 Man/ IC holding
Staff training (Requirement of trainer) As per training norms.
– ART & Accident relief, – Mill Wright, – Welfare measure, – Ancillary staff. – Existing norms for ART & Accident relief – Balance activities to be on need basis.
Linen ManagementPer AC Coach holding0.18/ AC Coach holding* * Zonal Railway to consider outsourcing this activity.

Note:

1. Leave reserve & rest givers may be provided as applicable in addition to above yardstick.

2. The norm does not cover Ministerial staff and Divisional Control staff. 

Activities to be outsourced

1. All coach cleaning and watering activities including en-route watering (Already identified for outsourcing).

2. Coach amenity attention including carpentry welding, trimming, plumbing/ pipe fitting and provision of items like window glass, mirror, bottle holder, snack table, taps and faucet etc.

3. Attention to fire extinguishers (Afready outsourced).

4. Linen washing and distribution (Already outsourced on most of the depots).

5. New amenity/ security activities like PA/ PIS, CCTV & infotainment etc.  