Track Maintainers: MCNTM

No.2019/CE-I/GNS/4, dated 28.06.2024

Sub: Modified MCNTM (Manpower and Cost Norms for Track Maintainers) Formulae 2024 – Norms/ Yardsticks for Track Maintainers.

1. In order to fix the norms for calculation of total requirements of the manpower of Track Maintainers, Board (DG/HR, MI, MF and CRB&CEO) has approved the Modified MCNTM (Manpower and Cost Norms for Track Maintainers) Formulae 2024 with details as under:-

(i) Strength of Track Maintainers shall be calculated using the Modified MCNTM Formulae as under:

[0.8(T) + (0.4R) + [M1 + M2 + M3 + 0.75M4 + M5 + M6 + 0*M7 + 0.5M8] + [0.8S1 + 0.5S2 + 0.5S3 + S4 + 0.8S5 + S6 + S7 + 0*S8 + S9 + S10]

(ii) The factors T, R, M & S has been defined in Annexure-I. Details for calculation of manpower requirement are available on Railway Board’s website. It may be accessed through the path: www.indianrailways.gov.in/railwayboard >> “About Indian Railways” >> “Railway Board Directorates” >> “Civil Engineering” >> “12. Trackmen Related Matters” >> MCNTM – Reports & Circulars.

2. In addition to the said formulae for calculating man power requirements Board (DG/HR, MI, MF and CRB&CEO) has also approved the following:-

(i)    Zonal Railways shall work out the requirement of manpower as per above new norms, every year as on 1st April,

(ii)    Zonal Railways may outsource the track maintenance activities listed in Table-1 & 2 of Annexure-II (in addition to Track maintenance activities allowed vide Board’s letter dated 02.04.2007, enclosed) to the extent of percentage of total scope as provided in enclosed Annexure-II. Sufficient fund as per estimate to be demanded & kept in newly created PU-32A for outsourcing of manpower. Till the creation of New PU-32A, fund may be demanded & kept in the PU-32.

(iii)   Funds equivalent to 75% of the salary saved due to shortfall in manpower (i.e. difference in manpower required as per Modified MCNTM norms & On-roll Strength) shall be demanded & kept in newly created PU-32A for outsourcing of manpower/ activities. Till the creation of New PU-32A, fund may be demanded & kept in the PU-32.

3. The requirement of funds to be workout out and demanded by Division in consultation with Principal Chief Engineer of Railways.

4. The modified MCNTM norms shall be reviewed again once maintenance as per Mobile Maintenance Units (MMUs) is fully in place.

5. Excel Sheet for the calculation of required manpower as per new norms will be provided on IRICEN portal in due course.

6. This issue with the concurrence of Finance Directorate of Ministry of Railways.

Annexure-I

Detail of T.R.M.&S.

Primary Maintenance ActivitiesAuxiliary Maintenance Activities
Activities T (Affected by Traffic density)*Activities M (Miscellaneous)
Activities R (Routine: Unaffected by traffic density)*Activities S (Site-specific)
Note: (i) *Combine multiplying factor for all activities under ‘T’ is 0.8 (ii) *Combine multiplying factor for all activities under ‘R’ is 0.4

‘M’ Activities & factors

Activities- MRecommended Factor
M1 – Monsoon Patrolling1
M2 – Hot Weather Patrolling of LWR track1
M3 – Cold Weather Patrolling of LWR track1
M4 – Watching Vulnerable locations0.75
M5 – Gate keeping at level crossings1
M6 – Rest giving for keymen1
M7 – Waterman duty0
M8 – Store-watchman duty0.5

‘S’ Activities & factors

Activities- SRecommended Factor
S1 – Tunnel maintenance0.8
S2 – Bridge substructure maintenance0.5
S3 – Long Girder maintenance0.5
S4 – Extra maintenance due to very sharp curve, deep cutting and steep gradients1
S5 – Maintenance of tack on extremely bad formation0.8
S6 – Lookout man duty1
S7 – Fogsignal man duty1
S8 – Filth removal from track0
S9 – Security patrolling1
S10 – Watching of water-level in suburban section1

Annexure-II

Zonal Railways may outsource the track maintenance activities listed in Table-1 & 2

Table-1

Main Line ‘T’ & ‘R’ Activities for outsourcing

ActivityDescriptionRecommended Outsourcing in %
T-1Slack attention33%
T-2For tie tamper working50%
T-3Casual Renewal33%
T-4Repair Welding0%
R-1Lubrication of ERCs100%
R-2Shallow screening of track100%
R-3Loading, leading, unloading0%
R-4Overhauling of level crossings100%
R-5Watching caution spot & Misc0%
R-6Tree cutting for visibility80%
R-7Lubrication of rails in curves0%
R-8Accident relief and carcass removal in run-over case0%
R-9Bridge sleeper attention and renewal0%
R-10Pre-monsoon attention, such clearing of drains and waterways, cess repairs, de-weeding of tack and attention to cuttings and trolly refuges50%
R-11Creep pooling (approaches of bridge, turnout)0%
R-12Rectifying damage to L/C posts and gates0%

Zonal Railways may outsource the track maintenance activities listed in Table-1 & 2

TabIe-2

Running Yard lines, ‘R’ activities for outsourcing

ActivityDescriptionRecommended Outsourcing in %
R-1Slack attention33%
R-2For tie tamper working50%
R-3Casual Renewal33%
R-4Lubrication of ERCs100%
R-5Lubrication of Rail Joints50%
R-6Shallow screening (1/5 length)100%
R-7Loading, leading, unloading0%
R-8Lubrication of rails in curves100%
R-9Pre-monsoon attention, such as clearing of drains and waterways, cess repairs, de-weeding of track and attention to cuttings and trolly refuges50%

Download Railway Board Circular dated 28.06.2024