Incentive: RBE No.122/2000 – Revision of Scheme

No.91/M(W)/964/126/Pt, dated 20.06.2000

Sub: Revision of Incentive Scheme.

Ref: Board’s letter of even number dated 17.12.1999 (RBE No.310/1999).

1.     The subject of review of Incentive Scheme at Wheel & Axle Plant has been reconsidered by the Board. The Board has now decided as under:-

(i) The plant capacity and standard man-hours shall be as follows:-

Plant Capacity 
Wheel8300/month
Axle4200/month
Standard Man-hours 
Wheel shops87414
Axle shops41724

These shall be subject to annual review.

(ii) No Bonus limit shall be 83% of plant capacity.

(iii) Incentive rates shall be based on the minimum of the pay scale of Gr.II operator and shall be:

Wheel shopsRs.0.58/wheel
Axle shopsRs.1.15/axle

1. These changes will be made applicable w.e.f. 01.09.1999.

      3.     All other factors would remain same as conveyed vide this office letter referred to above.

      4.     This issues with the concurrence of Finance Directorate.