RBE No. 20/2005: Refresher Courses – Safety Categories

No. E(MPP)2003/3/35, dated 31.01.2005

Sub: Refresher courses for safety categories.

In partial modification of Board’s letter No.E(MPP)2003/3/35, dated 28.05.2004 (RBE No. 109/2004), it has been decided that:-

(i) Item No.3 JE/ SE/ SSE Track Machines should be read as “Track Machine Maintainers/ Technicians”.

(ii) Item 6 (Track Machine Operators) should be read as “JE/ SE/ SSE Track Machines”.

With the above corrections, the duration and periodicity for the purpose of refresher courses of Civil Engineering staff would be as follows:-

Sl. No.

Category

Duration of the course

Periodicity

Medical Classification

1.

JE/ SE/ SSE Bridges

18 working days (3 weeks)

Once in 5 years

A-3

2.

JE/ SE/ SSE P. Way

12 working days (2 weeks)

Once in 5 years

A-3

3.

Track Machine Maintainers/ Technicians

12 working days (2 weeks)

Once in 5 years

A-3

4.

Gate Keeper/ Trolleymen

12 working days (2 weeks)

Once in 5 years

A-3

5.

PWMs, Mate Keyman, Gangman

12 working days (2 weeks)

Once in 5 years

B-1

6.

JE/ SE/ SSE Track Machines

12 working days (2 weeks)

Once in 5 years

A-3

This has the approval of Civil Engg. and Safety Directorates of Railway Board.

The Ministry of Railways have decided to modify the “Manual of Management of Training” (Edition 1998) as per the Correction Slip No.2/2005 enclosed.

Advance Correction Slip No.2/2005

Manual on Management of Training

(June, 1998)

Part I of the Appendix-III of the Manual on Management of Training (Edition – 1998) may be replaced as under:

Sl. No.

Category

Duration of the course

Periodicity

Medical Classification

1.

JE/ SE/ SSE Bridges

18 working days (3 weeks)

Once in 5 years

A-3

2.

JE/ SE/ SSE P. Way

12 working days (2 weeks)

Once in 5 years

A-3

3.

Track Machine Maintainers/ Technicians

12 working days (2 weeks)

Once in 5 years

A-3

4.

Gate Keeper/ Trolleymen

12 working days (2 weeks)

Once in 5 years

A-3

5.

PWMs, Mate Keyman, Gangman

12 working days (2 weeks)

Once in 5 years

B-1

6.

JE/ SE/ SSE Track Machines

12 working days (2 weeks)

Once in 5 years

A-3